Official letter No. 5110/BXD-KTXD dated November 11th, 2022 of the Ministry of Construction regarding guidelines on adjustment to time of construction contract performance
Posted: 17/11/2022 11:25:52 AM | Latest updated: 13/12/2022 10:03:57 AM (GMT+7) | LuatVietnam: 5586 | Vietlaw: 591
VietlawOnline

According to the regulations at clause 1 Article 14 of Decree No. 37/2015/ND-CPstatus2 , time of construction contract performance is counted from the effective date of the contract till the parties have fulfilled their obligations under the signed contract.

The effective date of a contract is the date when it has been signed (affixed with stamp if any) or other specific times as agreed in the contract and the employer has received performance bond issued by the contractor (for a contract with provisions on performance bond being specified) (Article 6 of Decree No. 37/2015/ND-CPstatus2 ).

The adjustment to a construction contract shall be carried out according to the contents of the signed contract in line with invitation documents, bidding document and regulations of laws provided for contracts.

Ms Phuong Thao (VietlawOnline.com)
Please tag VietlawOnline.com for reposting this article

Related documents

Penalty document

Unknown

Information

Effective Date Unknown
ExpiredDate Unknown
Published Vietlaw's Newsletter No. 591

Files attachment

enflag pdficon CV5110_11112022BXD[VLO].pdf

Timeline

No data

Construction

blue-check Roadmap for application of BIM in construction sector
blue-check Strategy for development of science, technology and innovation in construction industry by 2030
blue-check List of documents on construction investment promulgated by the Ministry of Planning and Investment between November 1st, 2021 and November 1st, 2022
blue-check Regarding signing of construction contracts and annexes thereof with regard to a partnership of contractors
blue-check How to do in case a member in a partnership of contractors does not agree the extension of a construction contract
blue-check How to determine time of construction contract performance
blue-check Regarding conditions for issuance of construction planning practicing certificate
blue-check Bases for determination of unit labor costs of construction consultant experts
blue-check Issue relating to payment for warranty of construction works
red-check From August 8th, 2022: Fee for grade adjustment to certificate of construction capacity shall be increased to 1,000,000 VND
blue-check It is required to ensure the net building density for construction of factories not exceeding 70%
blue-check
blue-check Issue relating to completion of construction works
blue-check Regarding application of foreign standards to construction works in Vietnam
blue-check How to calculate costs for making feasibility study report and construction design costs
blue-check Regarding regulations on calculation of costs of appraisal of construction projects
blue-check Some notes upon liquidation of a construction contract due to the contractor’s breach in the contract
blue-check Regarding modification of categories, origin in a construction contract
blue-check Order of priority application of documents enclosed with a construction contract
blue-check Investor has the right to unilaterally terminate the contract if the contractor delays construction work for 56 consecutive days